Work is to be carried out by qualified tradesmen to the quality and standards specified.
-
A contractor shall use tenders only from qualified subcontractors.
-
A bidder shall neither seek nor accept information concerning a competitor's bid prior to the opening of tenders.
-
A bidder shall never make known the tender of any subbidder to any subbidder before the closing of tenders; and shall never use the tender of a subbidder in order to secure a lower proposal from another subbidder.
-
Subcontractors shall be advised as soon as is reasonable after bid closing as to whether or not their bid was used in the making up of a successful prime contractor's bid; subtrade contracts should be awarded with the utmost possible dispatch.
-
A contractor should award each subcontract to the qualified subcontractor tendering the lowest price; if the award is made to any other subcontractor, it shall be at the latter's tendered price.
-
A contractor shall pay all subcontractors and suppliers, promptly and in accordance with the terms of the contract for their contracted work.
-
All services performed by one contractor for another where payment is required should be recorded and signed for at agreed intervals; agreement with regard to the payment for such job services should be reached and recorded in writing before such work commences.
-
The Alberta Construction Association Standard Subcontract Form or applicable CCA document should be used.